Tepco plans to increase the No. 6 reactor's output level to 50% before temporarily halting it on Friday or later to inspect ...
Tepco's Kashiwazaki-Kariwa Unit 6 has begun trial power transmission after neutron monitor glitch, with full output targeted by March.
Tokyo Electric Power Company has restarted unit 6 of its Kashiwazaki-Kariwa nuclear power plant in Japan's Niigata Prefecture ...
Tepco has restarted its Kashiwazaki-Kariwa NPP Unit 6 in Niigata after technical delays, aiming for commercial operation by ...
TOKYO -- Tokyo Electric Power Company (TEPCO) has resumed power generation and transmission to the grid from its Kashiwazaki-Kariwa nuclear plant in Niigata prefecture, central Japan.
Japan switched on the world's biggest nuclear power plant again on Monday, its operator said, after an earlier attempt was ...
Japan has taken a major step in its nuclear recovery after restarting unit 6 ...
Tokyo Electric Power Company Holdings Inc. said Monday it restarted the No. 6 reactor at its Kashiwazaki-Kariwa nuclear plant in Niigata Prefecture the same day after a series of control rod-related ...
Due to the malfunction, the planned start of power generation and transmission from the reactor is expected to be delayed by about half a day.
Operator says it does not know when the problem at the Kashiwazaki-Kariwa plant in Niigata province will be solved, after an alarm sounded during start-up The restart of the world’s largest nuclear ...
More than two weeks after the restart was suspended, Tokyo Electric Power Co. will resume operations for a second time on Feb. 9 at the No. 6 reactor of its Kashiwazaki-Kariwa nuclear power plant in ...
Japan suspended the restart of the world’s largest nuclear power plant just a day after it began operating for the first time since the 2011 Fukushima disaster, after an alarm sounded during start-up ...